Distributed Generation Customer Resources

The BTU Board and Bryan City Council recently approved changes to how customers with distributed generation systems less than 50 kilowatts (kW) will be compensated for excess energy their systems produce and export to the BTU electric grid. Utilize this page as a resource to find helpful information as the transition to this new compensation structure approaches.

Contact Us
Image
Installing Solar Photo

In June 2026, Bryan Texas Utilities (BTU) communicated to distributed generation customers via mail and/or email that the Bryan City Council approved a revised electric rate ordinance.  That ordinance changes how customers with distributed generation systems less than 50 kilowatts (kW) will be compensated for excess energy their systems produce and export to the BTU electric grid. 

Per this ordinance, all electricity imported from the grid into a customer’s home or business, will be billed at the applicable retail electric rate. Separately, all excess electricity generated by a customer’s distributed generation system, and returned to the grid, will receive a bill credit based on the current Power Cost Recovery Charge (PCRC) component of your applicable BTU electric rate.

The Bryan City Council approved a transition period for this compensation change at its meeting on July 14, 2026. All existing distributed generation customers will be assigned a transition scheduled determined by the date of installation of their residential solar systems:

Distributed System Installation Year

Transition Period Following Effective Date of Ordinance

Installed during 202672 Months
Installed during 202560 Months
Installed during 202448 Months
Installed during 202336 Months
Installed during 202224 Months
Installed in 2021 or earlier12 Months

How will I be compensated for excess generation under the new policy?

Image
This graphic diagrams a house with solar panels and explains how solar energy is generated, used, and credited under BTU distributed generation agreements

When you sign a Distributed Generation Agreement with BTU, you are signing up to be credited for the excess solar power you produce and export back to the grid. You have the first right to use the power you generate, and unless you are storing your excess power in a battery, everything you don't use is measured by your meter as it is exported. You do not have to lift a finger!

The power you pull from the BTU grid when your solar system is not producing enough for your current needs (supplemental grid consumption) is billed at the full retail rate, which includes the power you are using and pass-through charges that cover BTU expenses related to getting power where it needs to be.

The power you export to the BTU grid when you are not using everything your are generating at a given time (excess grid production) is purchased from you at the current Power Cost Recovery (PCRC) rate. This rate is the annual average cost of the fuel BTU uses to generate electricity and the cost to purchase electricity from other sources. The PCRC rate is higher than what you would receive if you hypothetically exported your solar energy directly to the ERCOT wholesale market.

Below are examples of what your bill could look like under the new compensation system in different scenarios, using round numbers and the City of Bryan Residential Rates for simplicity. You can substitute your rate (e.g. rural or College Station) and actual consumption and export data to see real results for yourself, or reach out to solar@btutilities.com for assistance in doing so.

Scenario 1: Customer Exports More Than They Consume

Consumption/Export Amount

Rate of Charge or Credit

Amount of Charge or Credit
500 kW Imported (Supplemental BTU Grid Consumption)Charged at $0.1097/kWhCharged $54.85
600 kW Exported (Excess Production Given to BTU Grid)Credited at $0.0376/kWhCredited $22.56

Availability Charge

$11.00

YOUR TOTAL BILL (Electric Only):

$43.29
Scenario 2: Customer Exports Exactly What They Consume

Consumption/Export Amount

Rate of Charge or Credit

Amount of Charge or Credit
500 kW Imported (Supplemental BTU Grid Consumption)Charged at $0.1097/kWhCharged $54.85
500 kW Exported (Excess Production Given to BTU Grid)Credited at $0.0376/kWhCredited $18.80

Availability Charge

$11.00

YOUR TOTAL BILL (Electric Only):

$47.05
Scenario 3: Customer Exports Less Than They Consume

Consumption/Export Amount

Rate of Charge or Credit

Amount of Charge or Credit
500 kW Imported (Supplemental BTU Grid Consumption)Charged at $0.1097/kWhCharged $54.85
400 kW Exported (Excess Production Given to BTU Grid)Credited at $0.0376/kWhCredited $15.04

Availability Charge

$11.00

YOUR TOTAL BILL (Electric Only):

$50.81

NOTE: Your amount for credit will be lower than the solar generation reported by your solar software algorithm. This is because your BTU meter measures, and BTU credits, only what you export to the grid. The rest of the generation reported by the solar software was likely consumed within your home or property. Additionally, most solar software algorithms report with at least a 5% margin of error. 

Frequently Asked Questions

Request a Breakdown of Your Bill

If you would like more information about the changes to the compensation structure for excess generation or how it will affect your monthly bill, please email solar@btutilities.com or contact Ken Dupré at (979) 821-5776.